EVM Analysis
Your company supplies swimming pools.
Save your time - order a paper!
Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines
Order Paper NowYou are in the process of managing the following project.
The review date is early Monday Week 2 before Install Pool is due to have started.
Project
WBS |
Scheduled Start |
Budget Cost (Planned Value) |
Actual Cost |
Started |
Completed |
||||
Hours |
Cost Per Hour |
Cost |
Hours |
Cost Per Hour |
Cost |
||||
Clear Site |
Monday Week 1 |
16 |
$90 |
$1,440 |
18 |
$90 |
$1,620 |
Yes |
Yes |
Dig Hole |
Wednesday Week 1 |
8 |
$180 |
$1,440 |
9 |
$180 |
$1,620 |
Yes |
Yes |
Smooth hole |
Thursday week 1 |
12 |
$80 |
$960 |
11 |
$80 |
$880 |
Yes |
Yes |
Install Pool |
Monday Week 2 |
14 |
$120 |
$1,680 |
11 |
$120 |
$1,320 |
Yes |
Yes |
Install Pipes |
Wednesday Week 2 |
12 |
$80 |
$960 |
14 |
$80 |
$1,120 |
Yes |
Yes |
Install Equipment |
Friday Week 2 |
8 |
$120 |
$960 |
No |
No |
|||
Install Paving |
Monday Week 3 |
24 |
$100 |
$2,400 |
No |
No |
|||
Landscape |
Thursday Week 3 |
16 |
$75 |
$1,200 |
No |
No |
|||
Total |
110 |
$11,040 |
63 |
$6,560 |
- What is the earned value (EV) for the project?
- What is the planned value (PV) for the project?
- What is the budget at completion (BAC)?
- What is Cost Variance (CV) for the project?
- What is the Schedule variance (SV) for the project?
- What is the cost performance index (CPI) for the project?
- What is the Schedule performance index (SPI) for the project?
- What is the estimate to complete (ETC) for the project predicting that the variance will continue?
- What is the estimated cost at completion (EAC) predicting that the variance will continue?