Sophisticated Skates produces a variety of inline roller skates. Management wants you to develop an aggregate plan for the next 7 months.
Save your time - order a paper!
Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines
Order Paper Now
Cost Data (per unit) |
||
Regular time labor cost per unit |
$9.60 |
|
Overtime labor cost per unit |
$14.40 |
|
Hiring cost per unit |
$2.00 |
|
Firing cost per unit |
$3.00 |
|
Inventory holding cost per unit per period |
$5.00 |
|
Shortage cost per unit per period |
$7.50 |
|
Material cost per unit |
$30.00 |
|
Capacity Data |
||
Previous month’s output |
4500 |
|
Beginning inventory (units) |
2500 |
|
Labor standard per unit (hours) |
0.64 |
|
Regular time hours available per period per employee |
160 |
|
Overtime hours available per period per employee |
20 |
|
Demand Forecast |
||
November |
3000 |
|
December |
6000 |
|
January |
2000 |
|
February |
1500 |
|
March |
4000 |
|
April |
5500 |
|
May |
8500 |
- Develop an aggregate plan using a level production strategy, inventories, and back orders. What is the level production quantity for the plan? Calculate the total cost of the plan.
- How many workers are needed for the level plan?
- Develop an aggregate plan using a chase production strategy. Change the production quantity each period to match that period’s level of demand. Calculate the total cost of the plan.
- Compare the two plans. Propose a hybrid plan.
Given data:
Type of plan (level, chase, hybrid):
Regular Production cost =
Overtime Production cost =
Subcontract cost =
Inventory carrying cost per unit per period =
(Backorder or Lost sale) Shortage cost per unit per period =
Hiring cost =
Firing cost =
Beginning Inventory: |
Beginning Workforce (by unit or empl): |
||||||||
Time period |
Demand |
Regular |
Overtime |
Subcontract |
Ending |
Backorder/ lost sale |
Workers |
Hire |
Fire |
November |
|||||||||
December |
|||||||||
January |
|||||||||
February |
|||||||||
March |
|||||||||
April |
|||||||||
May |
|||||||||
Total: |
|||||||||
Cost: |
|||||||||
Total cost of plan: |
- Compare the two plans. Propose a hybrid plan.