Question 181 pts Which of the following is NOT one of the basic Project Management Tradeoffs (elements of the Iron Triangle)? Group of answer choices Scope Cost Time Profit All of these are basic tradeoffs Flag question: Question 19 Question 191 pts A flow diagram of the sequence, inter-relationships and dependencies of the activities of a project is called the _________________________. Group of answer choices Resource histogram Basis of Estimate Work Breakdown Structure Project network Gantt chart Flag question: Question 20 Question 201 pts The Cost Reimbursable contract type would be most appropriate for which of the following projects: Group of answer choices Build a standard bridge Make a minor modification to an existing computer system Provide a haircut Add a specific capability to a previously developed software application Design a system which has never before accomplished before
 