Use this info for questions 9 through 13.

Chuck’s Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious New York real estate developer, Mr. T. Relevant data on the project are shown below. The complication is that Mr. T wants delivery in 30 weeks or he will impose a penalty of $250 for each week his yacht is late. Determine the lowest cost plan for crashing this project.

Save your time - order a paper!

Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines

Order Paper Now

Note: All numbers are in thousands, but keep them that way (i.e., don’t enter the last three zeros).

  • What is the expected project duration before crashing any activities?
  • What is the cost of the fourth crash?
  • What is the cost of the seventh crash?
  • What is the total cost of all crashes that should be done to minimize costs?
  • How much should be spent on penalties?
  • 13. Chuck’s Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious New York real estate developer, Mr. T. Relevant data on the project are shown below. The complication is that Mr. T wants delivery in 30 weeks or he will impose a penalty of $250 for each week his yacht is late. Determine the lowest cost plan for crashing this project. Note: All numbers are in thousands, but keep them that way (i.e., don’t enter the last three zeros). What is the expected project duration before crashing any activities? Crash Normal # Immediate Cost Activity Time Possible Predecessor Per (weeks) Crashes Week Crash Normal # Immediate Cost Activity Time Possible Predecessor Per (weeks) Crashes Week J 10 1 175 K K J 8 2 45 L J 5 2 60 M K 4 2 20 N L 6 2 55 ? M, N 5 2 265 Q P 7 1 70 Y P 8 2 35 N Q 6 1 95