dolution
dolution.
Question 2 :
An activity has an early start (ES) of day 3, a late start (LS) of day 13, and early finish (EF) of day 9, and late finish (LF) of day 19. The activity:Question 3 :
A Schedule Performance Index (SPI) of 0.75 means:Question 4 :
Earned Value (EV) for a new optic radar design project is calculated at $100,000 and the Actual Cost (AC) is $80,000. The Budget at Completion (BAC) is estimated at $200,000. What is the current CPI on this project?Question 5:
Given that, a project with Earned Value (EV) = 1000, Actual Cost (AC) = 700, and Planned Value (PV) = 800, which of the following is correct calculation of the schedule variance (SV).
"Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!"
