Larry Edison is the director of the Computer Center for Buckly College. He now needs to schedule the staffing of the center. It is open from 8 A.M. until midnight. Larry has monitored the usage of the center at various times of the day, and determined that the following number of computer consultants are required:

Time of Day Minimum Number of Consultants Required to Be on Duty
8 A.M.–noon 4
Noon–4 P.M. 8
4 P.M.–8 P.M. 10
8 P.M.–midnight 6

Two types of computer consultants can be hired: full-time and part-time. The full-time consultants work for 8 consecutive hours in any of the following shifts: morning (8 A.M.–4 P.M.), afternoon (noon–8 P.M.), and evening (4 P.M.–midnight). Full-time consultants are paid $40 per hour.

Save your time - order a paper!

Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines

Order Paper Now

Part-time consultants can be hired to work any of the four shifts listed in the above table. Part-time consultants are paid $30 per hour.

An additional requirement is that during every time period, there must be at least 2 full-time consultants on duty for every parttime consultant on duty.

Larry would like to determine how many full-time and how many part-time workers should work each shift to meet the above requirements at the minimum possible cost.

Formulate a linear programming model for this problem.

Let f1 = number of full-time consultants working the morning shift (8 a.m.-4 p.m.),
f2 = number of full-time consultants working the afternoon shift (Noon-8 p.m.),
f3 = number of full-time consultants working the evening shift (4 p.m.-midnight),
p1 = number of part-time consultants working the first shift (8 a.m.-noon),
p2 = number of part-time consultants working the second shift (Noon-4 p.m.),
p3 = number of part-time consultants working the third shift (4 p.m.-8 p.m.),
p4 = number of part-time consultants working the fourth shift (8 p.m.-midnight).

(Click to select) maximize minimize C = (Click to select) (40 x 8) (30 x 8) (30 x 4) (40 x 4) (f1 + f2 + f3) + (Click to select) (40 x 4) (40 x 8) (30 x 4) (30 x 8) (p1 + p2 + p3 + p4)

subject to (Click to select) f3 + p4 = 10 f1 + f2 + f3+ p3 = 8 f1 + p1 = 4 f1 + f2 = 4

(Click to select) f1 + p1 = 10 f1 + f2 + p2 = 8 f3 + p3 = 6 f1 + f3 + p3 = 8

(Click to select) f2 + f4 + p3 = 8 f2 + f3 + p3 = 10 f3 + f4 + p3 = 10 f2 + f3 + p3 = 8

(Click to select) f3 + f4 = 8 f3 + f4 = 6 f2 + f3 + p3 = 6 f3 + p4 = 6

f1 = 2p1

f1 + f2 = 2p2

f2 + f3 = 2p3

f3 = 2p4

f1, f2, f3, p1, p2, p3, p4 = 0